Marble / Sourcing guide

Control changes to a stone purchase order after approval

A revised drawing can describe a new requirement without establishing what happens to the original order. For a stone buyer, the difficult questions are often which pieces have already been made, which quantities remain open and who has accepted the proposed consequences. Use a change register to connect those answers. The workflow below is an editorial record-keeping approach; the parties must agree its responsibilities and how decisions are communicated.

Keep the accepted baseline and the request separate

Give each requested change an ID and reference the order line, drawing revision and material approval it would alter. Keep the accepted baseline intact. Describe the proposed difference in a separate field, identifying affected piece IDs, zones or selected specimens. Do not replace the original quantity or drawing reference while the request is still under review.

Record who raised the request, why, and the response needed. A site measurement correction, a finish substitution and a quantity increase may need different reviewers. Separate those decisions even when they arrive in the same email. Link supporting files to the change ID so that a later reader can find the actual request.

Ask what has already happened before pricing the change

Ask the fabricator for the affected pieces' current status, with the date and supporting record: material selected, layout prepared, cutting started, finishing completed or packed. Treat an unanswered status as unknown. Ask which affected work can still be held and obtain acknowledgement of the agreed instruction; sending a revised attachment does not confirm that work has stopped.

Request a separate response covering proposed rework or replacement, additional or unused material, quantities, price differences, packing changes and revised dates. Keep each response open until its responsible party confirms it. Do not calculate a final revised total from a partial response or assume that an unchanged unit price means there is no additional work.

Use statuses that distinguish discussion from release

Agree a small set of statuses with the people maintaining the register. These are proposed workflow labels, not contractual definitions. Name the reviewer for appearance, dimensions or technical details and the person authorized to accept commercial changes. Record their decisions separately where the responsibilities differ.

Suggested statusEvidence to keep
RequestedOriginal request, affected IDs and baseline revision
Under reviewOpen questions, responsible people and actual work status
Accepted; not yet releasedNamed decisions, agreed consequences and remaining release conditions
ReleasedExact replacement documents and acknowledgement from the receiving fabricator
Declined or withdrawnRecorded decision and confirmed instruction for the affected work

Reconcile quantities instead of overwriting the order

Compare the original quantity, proposed quantity and confirmed revised quantity in the same unit. Keep the affected quantity separate from the full order total. If some pieces are already finished, ask whether they remain usable, require further work or need another agreed disposition. Record the answer against their IDs rather than silently removing them from the schedule.

List any unresolved quantity explicitly. Follow accepted changes through the inspection brief, crate contents and receiving schedule. If an original piece and its replacement will both travel, distinguish their purposes and counting treatment. Include accessories and spares when they are affected. Do not let a revised purchase total conceal an undecided item.

Worked example: a revised marble vanity opening

Illustrative scenario: a buyer sends a different basin reference after approving a marble vanity drawing. The change record identifies the vanity piece and the accepted drawing revision. The fabricator reports that its original cutout is complete. The buyer therefore keeps the original piece on the register and requests a response about the proposed replacement, material selection, additional work, dates and the disposition of the finished piece.

The responsible drawing reviewer checks the new basin information. The appearance reviewer considers any new material selection. Commercial acceptance is recorded separately. Only the confirmed package is issued as the new release, with acknowledgement from the fabricator. The packing schedule is then updated to show what will actually be shipped. This example illustrates the record sequence; it does not establish whether a particular piece can be reworked or what the change will cost.

Close the change with a traceable handover

Issue a short release note listing the change ID, approved documents, superseded revisions, affected pieces and anything still on hold. Ask each affected recipient to confirm the version received. Keep a dated copy of that acknowledgement alongside the accepted response.

Before dispatch, reconcile the release note with inspection and packing records. Close the register entry only when the agreed follow-up evidence is available. Retain declined and withdrawn requests as history so that an old attachment cannot easily be mistaken for a current instruction.

Does emailing a revised drawing automatically change the stone order?

Do not treat delivery of an attachment as evidence of acceptance or workshop implementation. Use the communication and approval process agreed for the order. Record the requested change, the relevant decisions, the released revision and the fabricator's acknowledgement, while keeping unresolved work and quantities visible.

Sources & further reading

External references support attributed material facts and provide further context. The purchasing checklists are BZStone editorial guidance; they are not supplier commitments or installation designs.

    Continue with marble.

    Category overview ↗

    From reading to a clear request

    Bring the details.
    Shape the brief.

    Gather the intended use, actual material references, dimensions, quantity and destination. Keep unknowns visible so they can be resolved before approval.

    Prepare a sourcing brief